Case Study: Vessel / Rig: Mamola Serenity

Vessel / Rig: Mamola Serenity

Date: Feb 2013 | Project duration: 2 weeks

Logistics Support Services was retained to install a new crane on board the supply tug the Mamola Serenity. LSS imported the 20.5 / 70 mT Liebherr crane and arranged for the Liebherr technicians to assemble the crane parts here in Walvis Bay. We then loaded it onto a low bed truck and lifted it on board the vessel using one of Namport’s harbour cranes where it was installed by the technicians. We were responsible for co-ordinating the entire two week long project which entailed customs clearing, insurance, port authority clearance, security, abnormal load transport and stevedoring.