Case Study: Vessel / Rig: Seaways 22

Vessel / Rig: Seaways 22

Date: November 2013 | Project duration: 48 hours

The client requested that Logistics Support Services replace the wire cable aboard the anchor handler, the Seaways 22. LSS removed the old wire and then carried out an inspection on the winch. With a 120 ton spooling unit, we loaded 1400 metres of 52mm wire cable onto the vessel, but ultimately we needed to replace the winch would not operate with the spooler. This was a two day project in order to get the timing of the new winch correct.